Since mid-July, walkers heading north on the East River Esplanade from the new 71st Street ramp have reached about East 73rd Street before turning back at a construction wall. Our Town reported that the remaining blocks to East 78th Street were expected to reopen this fall. That wall has stood in some form since spring 2022, when Hospital for Special Surgery began closing the stretch to build its $200 million Kellen Tower.
October is the month HSS has set for finishing the job. When it does, the river path will be continuous through the East 70s for the first time in more than four years. NYC Parks has already scheduled the next round of work for that same waterfront, and its first section overlaps the last blocks HSS is completing.
How the East 70s have come back so far
The reopening has gone block by block, and the dates show how slowly it has moved:
- Spring 2022: HSS begins closing the seven-block stretch for the Kellen Tower expansion.
- July 2025: The 71st Street pedestrian ramp closes to the public.
- Spring 2026: The Kellen Tower, a 12-story clinical building over the FDR Drive near East 70th Street, opens.
- May 2026: Upper East Site reports that the reopening has been delayed again.
- June 15, 2026: The 71st Street ramp and the walkway from 70th to 71st reopen after final walkthroughs with the city's Department of Transportation and the Parks Department.
- Mid-July 2026: Access reaches about East 73rd Street. Parks Commissioner Tricia Shimamura toured the new paving on July 7 and told Our Town she expected the rest of the closure to be resolved by October.
The most recent official word is on HSS's project page. It still describes East 72nd to 78th Street as "closed during active construction," with reopening in phases and full completion "anticipated by October 2026." Community Board 8's Parks and Waterfront Committee did not take up the project's status at its September 10 meeting, and the October 8 agenda had no esplanade item. For now, October is a target, not a confirmed date.
The 78th Street bridge is the piece to watch
The last blocks of the job sit at the north end, beside John Jay Park, which faces the FDR Drive between East 76th and 78th Streets. At Community Board 8's June meeting, presenters said the 78th Street pedestrian bridge would close in July so crews could finish playground equipment and run irrigation lines underneath it. They added that it would not reopen until all eight blocks were done, and that they aimed to be finished and off the site by the end of October. The City Council's July 8 release said the same, stating that the bridge "will be closed starting this month."
Since then, no public notice has confirmed when the bridge actually closed or when it will reopen. When it does reopen, that will most likely mean the HSS project is finished, because the bridge was scheduled to stay shut until the whole stretch was complete.
What the reopened blocks will have
HSS's improvements north of 72nd Street go beyond replacing the fence with fresh pavement. According to the hospital, the work includes:
- Repairing a sinkhole near the base of the East 78th Street ramp and improving the seawall, coordinated with NYC Parks
- New pavers and landscaping
- Fitness equipment along the path
Parks has already repaired an earlier sinkhole at East 74th Street. In June, East Side Feed reported several smaller changes on the way. The Con Edison building beside the path was set to be repainted a Parks-approved beige later that month. The chain-link truck gate near that building was to be swapped for a heavy-duty movable crash barrier, which addresses a long-standing neighborhood concern about how little separates the narrow path from the highway. A new irrigation system was also planned for a stretch where plantings have struggled.
All of this builds on the roughly $1.8 million HSS spent restoring the 70th-to-72nd Street stretch in 2018. Once the East 70s are done, the Council expects a continuous esplanade from East 53rd Street to East 114th Street in late 2026. That route would link the East Midtown Greenway, which opened at the end of 2023, with Carl Schurz Park between East 84th and East 90th Streets, home to Catbird Playground and Gracie Mansion. It also passes the NYC Ferry landing at East 90th Street and the FDR Drive.
The seawall project starts where HSS ends
HSS is responsible for the walking surface. NYC Parks is responsible for the structure underneath, and Parks has its own project for that.
At CB8's March meeting, Parks announced that its East River Esplanade Phase 3 seawall repair project had an official order-to-work date of April 13, 2026. The project addresses deteriorating piles and seawalls in three sections, starting with 76th to 81st Street in coordination with HSS. Parks estimated 10 to 12 months of work for each section.
| Phase 3 section | Order | What's nearby |
|---|---|---|
| East 76th to 81st Street | First, coordinated with HSS | John Jay Park, 78th Street bridge |
| East 62nd to 64th Street | Later | Just north of Andrew Haswell Green Park |
| East 90th to 94th Street | Later | North end of Carl Schurz Park, the East 90th Street ferry landing |
The first section overlaps HSS's work for two blocks, from 76th to 78th Street, and continues three blocks past it to 81st. If that section started on schedule in April, 10 to 12 months of work would run into early 2027, after the HSS fence is expected to come down. NYC Parks' capital project tracker lists the overall project with an April 2026 construction start, a projected April 2028 completion, and 0 percent progress. The tracker shows no update date, so that figure may lag what is happening on site.
The most important detail for daily use is how Parks plans to do the work. In March, a Parks engineer told the committee that the contractor would work mainly from the water, that no pedestrian closures were planned, and that the walkway might narrow during top-side work on railings and pavers but would stay passable. That was the plan as of March, and no later report has described conditions on the ground. If it holds, the next phase will look very different from the last four years. Barges and crews may be working offshore while the path stays open, possibly narrowed in spots.
Friends of the East River Esplanade, the waterfront conservancy for the Upper East Side and East Harlem, has a petition on its homepage calling for faster reopening, better lighting and more green space along the path. The group plans to be out on the water's edge this month.
October on the esplanade
The group's three remaining October events are all on stretches that are open now:
- Saturday, October 17: Free bird walk with NYC Bird Alliance. The group meets at East 96th Street and the esplanade to look for water birds just offshore.
- Saturday, October 24: Spooktacular at Andrew Haswell Green Park. The event is at East 60th Street and the esplanade at York Avenue, with live music by NOIZ, kids' activities and free ice cream.
- October 31: Bulb planting. Volunteers plant daffodils and native species that will bloom along the esplanade in spring.
The bird walk and the Spooktacular are at opposite ends of the neighborhood's waterfront, 36 blocks apart, with the East 70s construction between them. For now, getting from one to the other along the river still means a detour at the HSS fence. Schedules for all three are on the EsplanadeFriends events page.
If you live near the river and want to understand how a fully restored waterfront figures into what your apartment is worth, Julio Izquierdo can walk through the numbers with you, building by building. Start with an instant home valuation.